Week 5

· 2 min read
Ella Apykhti

The final prototype is almost done, and we have just slightly over a week until our final presentation. We set out to test all our functionality and to add a few last finishing touches, and then to deploy and evaluate the final prototype.

Goals

  • Test and troubleshoot functionality on mobile and wide-screen devices
  • Add automatic image filtering
  • Add user notifications
  • Localize all strings to all four languages
  • Deploy the final prototype
  • Begin conducting evaluations of our prototype

Tasks

Ella

  • Test all functionality and report issues
  • Add automatic image filtering
  • Translate strings into Russian
  • Deploy the website with Sarah
  • Test functionality on deployed version
  • Evaluate Russian users

Kayla

  • Test all functionality and report issues
  • Add user notifications
  • Fix CRON jobs being lost when server restarts
  • Test functionality on deployed version

Miranda

  • Test all functionality and report issues
  • Translate strings into Spanish
  • Test functionality on deployed version
  • Evaluate Spanish users
  • Begin compiling information for project website

Sarah

  • Test all functionality and report issues
  • Finalize evaluation plan and surveys
  • Translate strings into Chinese
  • Deploy the website with Ella
  • Test functionality of deployed version
  • Evaluate Chinese and English users

Challenges

  • There were the regular issues with deployment and making sure everything was still working, but we were able to resolve them in the course of our initial deployment session.
  • Everything else went smoothly.

Reflection

This was a very productive week! We have our final prototype and most of our evaluations completed and are ready to put together the final presentation, report, video and website.